According to Pars Oil and Gas Company, CEO Touraj Dehqani maintained regular visits to the Phase 14 refinery and other ongoing projects during the conflict. He also inspected facilities damaged in the war and held separate meetings with subcontractors to plan the reconstruction of affected sections.
The report said gas injection from Phase 14 into the national grid resumed just 10 days after the refinery facilities were struck during the 12-day conflict. This was achieved by repairing and bringing three of the four sweetening trains back online. Since then, reconstruction of the fourth train has continued at full capacity.