Tabnak gas field separation center inaugurated with €85m investment

SHANA (Tehran) – The Tabnak gas field separation center, built with an €85 million investment, was inaugurated by videoconference on the order of the president.

The Tabnak gas field separation center was inaugurated today (Saturday, 7 Azar) by videoconference. President Masoud Pezeshkian and Hamid Bovard, caretaker oil minister, attended. The project aims to raise the reservoir's recovery factor, sustain production capacity and prevent a decline in gas output. Once in operation, it will allow an additional 17 billion cubic meters of gas to be produced from the field.

The Tabnak gas field measures 44 by 6 kilometers. It lies 40 kilometers north of Parsian county (Gavbandi), south of the Varavi gas field and east of the Assaluyeh field. It was discovered in 1999 (1378) and entered production in 2003 (1382).

Initial gas in place at Tabnak is estimated at 20.7 trillion cubic feet (586.2 billion cubic meters). Ultimate recoverable gas is put at 16.8 trillion cubic feet (475.7 billion cubic meters).

Production figures show that 9.1 trillion cubic feet (257.7 billion cubic meters) of gas and 133 million barrels of gas condensate have been extracted from the field so far.

17 bcm of Additional Gas Recovery from Tabnak

Because of falling reservoir pressure and rising water production from the wells, continued output from Tabnak would have faced constraints without maintenance and operational improvement projects. Daily gas production was projected to fall in 2027 (1406) from about 33 million cubic meters at present to 26–28 million cubic meters.

The separation center will make it possible to sustain daily production of 35 million cubic meters in 2027 and 2028 (1406 and 1407). The project will also raise the field's ultimate recoverable gas from 14.2 trillion cubic feet to 14.8 trillion cubic feet.

In this way, the separation center will yield around 600 billion cubic feet, equal to 17 billion cubic meters, of additional gas from the field. The reservoir's ultimate recovery factor will rise from 68.5 percent to 71.5 percent.

Plan to Raise Production to 36 mcm per Day

The development and production-maintenance program for Tabnak does not end with the separation center. A gas pressure-boosting station with a capacity of 36 million cubic meters per day is planned for winter 2030 (1409).

Once the station comes online, the field will be able to raise and sustain daily output at 36 million cubic meters for seven years. Cumulative gas production at the end of the field's life will reach 16.8 trillion cubic feet, about 475 billion cubic meters.

According to reservoir estimates, the combined separation center and pressure-boosting projects will lift the field's ultimate recovery factor to 81.1 percent. Cumulative gas condensate production at the end of the field's life will reach about 201 million barrels.

€85m Private-Sector Investment

A total of €85 million has been invested in building and commissioning the Tabnak separation center. The project was carried out under an engineering, procurement, construction and finance (EPCF) contract using private-sector investment, with a stated annual internal rate of return of 8 percent.

Besides building and commissioning the separation center, the scope covered a power distribution substation, a 19-kilometer, 11-kV power transmission line and a 21-kilometer gas condensate pipeline.

Construction took about five years and drew on the technical expertise of Iranian engineers, specialists and workers.

During the project, 860,000 cubic meters of rock excavation and earthmoving, 710,000 cubic meters of filling and bed preparation, and 21,000 cubic meters of concrete pouring were completed.

Other work included 2,500 tons of rebar, the installation of 2,200 tons of static and rotating equipment, tanks and steel structures, and 9,000 square meters of industrial buildings and concrete structures.

On the pipeline and facilities side, 21 kilometers of pipeline were laid and a total of 119,000 inch-diameters of welding was completed. In addition, 295,000 meters of power and instrumentation cable were installed at the center.

The commissioning of the Tabnak separation center is an important step in protecting the country's gas reserves, raising the reservoir's recovery factor and sustaining gas output in the Iran Central Oil Fields Company's area. By preventing a production decline in the coming years, the project lays the groundwork for maximum recovery from the field's capacity.