SHANA (Tehran) – The managing director of the National Iranian South Oil Company (NISOC) has announced that 29 flares have been extinguished since the start of the 14th administration. The work involved $265 million in non-government investment and recovered about 260 million cubic meters of flare gas.

Ramin Hatami spoke Saturday at the inauguration of the Marun 3 and 5 flare gas recovery project. The ceremony was held by videoconference with President Masoud Pezeshkian and Hamid Bovard, caretaker oil minister, in attendance. Noting that NISOC accounts for 70 percent of the country's crude oil production and a large share of its associated gas, Hatami said the company had pursued flare gas recovery projects seriously, in line with the president's strategy since the start of the 14th administration and the emphasis placed on the issue at NIOC level.

He added that since the start of the 14th administration, various projects backed by $265 million in non-government investment have recovered about 260 million cubic meters of flare gas and extinguished 29 flares.

The NISOC managing director said the effort has reduced environmental risks and also completed the value chain. The projects bring NIOC about $188 million in revenue a year.

Referring to the four new Marun 3 and 5 flare gas recovery projects, Hatami said that besides preventing the flaring of 30 million cubic feet of gas and extinguishing four flares, they generate about $22 million in annual revenue. They have also created lasting jobs for 140 people, mostly local and skilled workers.

On the use of domestic capacity, he said about 60 percent of the equipment used in the projects is Iranian. He voiced hope that future projects will see facilities commissioned with entirely Iranian equipment, which he said the skill and dedication of the country's young specialists can achieve.

The NISOC managing director also announced that 19 flare gas recovery projects, with $450 million in investment, were handed over to the private sector in 2025 (1404). Once complete, they will collect 318 million cubic feet of gas and generate about $190 million in revenue.

On the timeline, Hatami said the first of these projects will be commissioned by the end of Bahman (mid-February 2027), and the rest will come on stream gradually over the coming year.

He said these results came in the country's unusual circumstances and through the tireless work of oil industry staff. His colleagues, he said, did not stop for a moment, and the continuation of their work has now borne fruit.

Hatami went on to say that plans have been drawn up to help reduce the gas imbalance. Following the caretaker oil minister's order to reduce the imbalance under current conditions and to help meet part of the needs of the gas grid and industries, he said, innovative programs have been developed and carried out at the company.

He added that thanks to his colleagues' efforts, up to 20 million cubic meters of gas will be added to the country's consumption grid before the peak of the cold and the start of the peak consumption period.