Downhole pumps lift Azadegan capacity by over 5,000 bpd

SHANA (Tehran) – The commissioning of the fourth downhole pump in the joint Azadegan oil field in just 12 days has brought the total production-capacity increase from installing this equipment in four wells to more than 5,000 barrels per day. It is a valuable achievement in the continuing development programs and efforts to improve well productivity at this strategic field.

Azadegan, one of the country's largest oil fields and among the most important development projects of the oil industry in the West Karoun region, has remained in the spotlight in recent years thanks to programs to raise production, develop wells, and complete surface and processing infrastructure. The field is shared with Iraq, and protecting Iran's share of the shared reserves has made accelerating its development and increasing recovery one of the National Iranian Oil Company's priorities.

The inclusion of Azadegan's development in the list of the country's 20 major driver and foreign-currency-earning projects reflects its economic and strategic standing in national development plans. Accordingly, each stage of its development projects firms up the steps toward final development.

Output Up by More Than 5,000 Barrels with Four Pumps

In the latest operational move, the fourth downhole pump in the Azadegan field was successfully commissioned after 12 days of installation and running operations. With downhole pumps installed and started up in four wells, more than 5,000 barrels per day have so far been added to the field's production capacity.

Esmaeil Gholampour Ahangar, Azadegan oil field development project manager, said that installing and running a downhole pump once took up to 50 days in some cases. Under agile-management measures and the optimization of subsurface programs, the time was cut to 25 days, and the latest operation was completed successfully in 12 days.

Stressing the importance of shorter operation times, he added that faster installation and startup of the pumps, together with higher well output, is an effective step toward optimizing operational processes and raising the field's production capacity.

Earlier, the third downhole pump had been installed and commissioned in well No. 141, and its operation raised the field's daily output by about 800 barrels.

Nearly Fourfold Output Increase in the First Pump-Equipped Well

Electric submersible pumps (ESPs) were adopted in Azadegan to strengthen oil flow, compensate for pressure decline, and raise output from wells facing natural-production limits.

In the first phase of this program, well AZNS-156 was fitted with a 130-horsepower downhole pump. Installation and startup ran from 4 to 23 Mehr 1405 (September 26 to October 15, 2026), a period of 20 days, after which the well entered the production cycle.

The result was a rise in the well's daily output from 435 barrels to 1,710 barrels. Production thus increased by 1,275 barrels per day, reaching nearly four times its previous level.

This increase in the first pump-equipped well demonstrated the value of the technology in improving well productivity in the field. By providing the force needed to lift fluid to the surface, downhole pumps help offset pressure decline and strengthen oil flow, making it possible to raise output from wells whose natural production capacity has declined.

Processing Capacity Expanded Alongside Well Output

Raising well output without expanding oil receiving and processing capacity cannot, on its own, meet the field's development goals. Completing surface facilities and processing units has therefore been pursued alongside subsurface activities in Azadegan.

To this end, with the startup of all four oil trains of the Azadegan South Central Processing Unit (CTEP) completed, its nominal oil processing capacity reached 320,000 barrels per day. Each of the four trains can process 80,000 barrels of oil per day.

Before the complex was completed, processing trains C and D, with a combined capacity of 160,000 barrels per day, had come on stream. With the startup of trains A and B, the unit's nominal oil capacity rose to 320,000 barrels per day. By enabling the receipt and processing of larger volumes of produced oil, these facilities are among the key infrastructure for developing Azadegan South.

Higher Output Built on Existing Capacity

Taken together, the measures carried out in Azadegan, from installing downhole pumps and raising the productivity of existing wells to shortening operation times and completing processing capacity, show that raising the field's output is not limited to drilling new wells. Making optimal use of the capacity of producing wells also has an important place in its development plan.

Indeed, the experience of installing four downhole pumps and adding more than 5,000 barrels per day, along with cutting installation and startup time to 12 days, underscores the combined importance of technology, operations management, and productivity in developing oil fields. This approach can open the way to higher output from existing capacity by speeding up the execution of operational programs.

With Azadegan holding special importance in the country's oil production plans because it is shared with Iraq, an increase of more than 5,000 barrels per day from four downhole pumps and a cut in the latest operation to 12 days is an example of what can be achieved through better productivity and faster execution of the field's operational projects.