Ahmadreza Rasti spoke today (Tuesday, November 17) at the ceremony inaugurating the early production phase of the Gurzin gas field's surface development. Describing the difficult conditions under which the project was carried out, he said: Construction work began in April 2025 and, despite the 12-day war and the subsequent 40-day war and the country's continuing exceptional circumstances, the project reached the early production stage through the efforts of IOOC staff and the project contractor.
Expressing appreciation for the engineering and construction teams, the project managers in the region and the contractor's workforce, he added: The project was completed while the country faced restrictions and hardships stemming from wartime conditions, which shows the dedication and solidarity of the employer and the contractor in advancing operational projects.
The IOOC managing director noted that early production from Well No. 9 of Gurzin has begun at a rate of about 10 million cubic feet per day, and stressed: Adding this volume of gas to the national grid on the eve of the cold season, as consumption rises in the northern provinces, carries particular importance.
Referring to the role of financing in moving the project forward, Rasti said: Members of the company's board supported the contractor in securing the necessary funding, and despite certain constraints and difficulties linked to the nature of the project, efforts were made to provide the resources needed to complete the work.
Stressing that contractors are part of the oil industry family, he added: Cooperation and synergy between employer and contractors are highly important in carrying out operational projects, and the early production from Well No. 9 of Gurzin is the result of this joint effort.
Plans to develop Qeshm's gas fields
Referring to the company's development plans in the Qeshm region, the IOOC managing director said: Alongside the inauguration of this project, development schemes for the region's fields are also on the agenda, so that the existing capacity of Qeshm's oil, gas and refining facilities can be used to better effect.
Rasti continued: In cooperation with the Investment and Business Management Directorate of the National Iranian Oil Company (NIOC), and following up on the matter, we are trying to identify and implement projects that deliver good returns on lower investment, so that the capacity of the region's existing facilities is preserved and their continued operation is ensured.
He announced that a contractor has been selected and a contract signed for deploying a drilling rig to the region, adding: The rig will soon be moved to the area so that drilling of gas Well No. 10 can also begin. Development plans are likewise being pursued in the Salakh area.
Completing the 10-inch gas pipeline a priority
Pointing to the importance of completing the 10-inch gas transmission pipeline in the Qeshm region, the IOOC managing director said: Completing this pipeline is among the company's priorities and must be finished as quickly as possible.
Expressing appreciation for the staff of the Qeshm region, operations managers, support units, security personnel and contractors, Rasti emphasized: Continued cooperation and solidarity among the executing teams can pave the way for completing ongoing projects and achieving the company's development goals in the Qeshm region.
Your Comment