1st Gas Sweetening Train of South Pars Phase 14 Refinery Online by July

TEHRAN (Shana) -- The CEO of Pars Oil and Gas Company said the first gas sweeteners of phase 14 of South Pars gas field will be handed over to the start-up group in July.

According to Pars Oil and Gas Company, Mohammad Meshkinfam, underlining the activities of the contractors of South Pars Phase 14 Refinery in different land fronts of the project, said: “According to the plan, the first train of gas sweetening of Phase 14 will be handed over to the commissioning groups by July and then the commissioning activities will continue in order to prepare the different units of this train.”

"Fortunately, the ancillary units of Phase 14 of South Pars are now ready to be launched. Also, the reception facilities, according to the contractors' commitment, will be ready to receive gas by June,” he said.