According to the South Pars Gas Complex Company, Mohammad Nemati stated that the overhaul aims to ensure stable gas production in the second half of the year and during the cold season. The project will be carried out in two phases, A and B, each lasting 11 days, with a full seven-day shutdown of the refinery.
Nemati provided details on work orders across various units, noting that 1,948 work orders will be executed, including 1,427 corrective, emergency, and technical inspection orders, along with 521 preventive maintenance orders. Additionally, 1,363 equipment tags have been assigned for process monitoring and control.
The manager emphasized that the maintenance adheres to safety and environmental standards and relies entirely on domestic engineering expertise. This approach reduces downtime, cuts costs, and enhances sustainable performance.