Four flare gas recovery projects start up at Marun 3, 5, capturing about 30 mcf per day

SHANA (Tehran) – The start-up of four flare gas recovery projects at Marun 3 and 5 has created capacity to collect about 30 million cubic feet of gas per day.

The four flare gas recovery projects at Marun 3 and 5 were inaugurated today (Saturday, 7 Azar) by videoconference, with President Masoud Pezeshkian and Hamid Bovard, caretaker oil minister, in attendance. The projects involve private-sector investment of about $46 million and are projected to earn the National Iranian Oil Company (NIOC) $22 million a year.

Of the four projects' combined capacity, 23 million cubic feet per day belongs to two gas collection and pressure-boosting projects, and 7 million cubic feet to two sweetening projects. Three projects, with a combined capacity of 26 million cubic feet per day, are at Marun 3, and one, with a capacity of 4 million cubic feet per day, is at Marun 5.

The projects fall within the operational area of the Marun Oil and Gas Production Company and form part of the flare gas recovery program of the National Iranian South Oil Company. Their aim is to stop flaring, cut waste, protect hydrocarbon resources and make the gas available for use.

An Important Step in Flare Gas Recovery

Flare gas recovery is among the Oil Ministry's priorities for protecting national resources and improving the productivity of the country's production capacity. Through various flare gas recovery projects in operating areas, the ministry is developing the infrastructure needed to reduce the volume of gas sent to flares and return it to the consumption cycle. Associated and flare gas recovery has become a key part of the ministry's executive agenda in recent years. It relies on investment, expanded processing infrastructure, activation of private-sector capacity and region-specific projects. Its effects are visible in higher recovery capacity, feedstock supply for downstream industries and less gas flared in the oil-rich regions.

Official figures put the volume of associated and flare gas now being recovered at more than 17 million cubic meters per day. Together with projects under way and contracts already signed, this shows the oil industry's continued push to meet the requirements of the Seventh Development Plan and make maximum use of the country's hydrocarbon resources. In line with this policy, the Marun 3 and 5 projects, by completing part of the infrastructure needed in this operational area, make it possible to collect and process associated and flare gas. They also open the way to economic use of the recovered gas, so that alongside reduced flaring they create wealth, preserve hydrocarbon resources and lessen environmental impact.

Collection and Pressure Boosting of 23 mcf per Day

One of the main components is the collection and pressure boosting of associated gas at the Marun 3 field. The Asmari second-stage sweet gas collection project, with a capacity of 15 million cubic feet per day, is the largest in the package. The Marun 3 Bangestan low-pressure gas collection project, at 8 million cubic feet per day, makes up the rest of the collection and pressure-boosting capacity.

Together, these two projects make it possible to collect associated gas and boost its pressure, so that it reaches processing and consumption routes under suitable operating conditions.

Another project is devoted to processing sour gas. The Marun 3 Asmari second-stage sour gas sweetening project has been built with a capacity of 4 million cubic feet per day. The Marun 3 Asmari second-stage sour gas collection project has also been completed, with a sweetening capacity of 3 million cubic feet per day.

Private-Sector Investment and Local Jobs

The package was carried out with about $46 million in investment from the private sector and the buyers of flare gas. Using investors' capacity to expand associated gas collection and processing facilities is one of the routes the National Iranian South Oil Company is taking to reduce flaring in its operating areas.

The projects are expected to generate about 6 trillion tomans ($22 million) a year in revenue for NIOC. More than 140 local workers have also been employed through them.

The four Marun 3 and 5 projects were commissioned to reduce flaring, protect hydrocarbon resources and raise the economic value of associated gas in the southern oil-rich regions.

News ID 3316948