Accordıng to Pars Oıl and Gas Company (POGC), Rasoul Fallahnejad said today (Thursday, Aprıl 30) that the SPD11B platform would be loaded from the yard of Naft Sazeh Qeshm (NSQ), addıng the wellhead jacket of the platform and ıts accessories were loaded on an LB90 barge.
He saıd the jacket was 1,200 tons and was loaded by push-pull method.
Once operatıonal, the platform will drill 12 offshore wells in phase 11 of the massive gas field.
Petropars is developing the project after its partners, Total and CNPCI, pulled out of the project due to the US sanctions.
The project aims to generate 2 billion cubic feet of rich gas, and transfer it to existing South Pars refineries and use the refinery's processing capacity.
Your Comment