According to the Pars Oil and Gas Company (POGC), Payam Motamed said Platform 13C was the fourth and last platform of the project.
He said the 2,500-ton satellite structure was installed using an HL5000 barge.
Having reached 98% completion, the platform was loaded at the yard of SADRA together with 13A Platform last month using a Push/Pull method, Motamed said.
Once Platforms 13A and 13C come on stream, the phase’s gas output will increase by 28 mcm/d. The phase is developed for 56 mcm/d of gas production capacity.
Your Comment