According to the Petroleum Engineering and Development Company (PEDEC), Keyvan Yarahmadi said the field’s output would reach 65,000 b/d soon given inauguration of the new facilities.
He said the LP and HP flares of the unit were set in motion after carrying out all the related operations including piping, mechanical section, instruments supply and pre-commissioning tests.
He said the LP flare was 37 meters high and had a 16-inch gas riser and a 28-inch air riser.
The HP flare is 72 meters high and has a 28-inch gas riser and a 42-inch air riser.