3rd Phase 14 Platform Loaded

TEHRAN (Shana) -- The operator of Phase 14 development project of South Pars gas field said the third platform of the offshore field was loaded for installation in its designated spot.

According to the Pars Oil and Gas Company (POGC), Mohammadi Mahdi Tavassolipour said Platform 14B of the phase was loaded at ISOICO’s yard in Bandar Abbas, south Iran, and was planned to be installed by the end of the current month of Khordad to June 21.

He also said that an HL-5000 barge was carrying the 2,400-ton platform.

Once operational, the platform will produce 500 million cubic feet (an equivalent of 14.1 million cubic meters per day) of natural gas.

He said Platform 14D was also being built at the yard of SADRA company and was in its final stages and would be ready for delivery by late September.