The company also announced that the offshore section of Phase 19 which is being developed by IOEC has achieved 90 percent progress.
Phases 20 and 21 of the South Pars were developed from 21 percent to 86 percent during the period and pipeline laying was completed for 203 kilometers.
Also Phase 14 developed for 65 percent and phases 22-24 developed up to 98 percent, IOEC said.