Construction will begin soon, and gas deliveries from the Northeast Gateway facility to
The LNG facility will be designed to handle peak deliveries of as much as 800 MMcfd of gas. During normal operations the facility will be able to deliver about 500 MMcfd of gas, or 20% of
The port"s infrastructure will feature two submerged turret loading buoys supplied by Advanced Production & Loading Inc.
Excelerate Energy will build and own the Northeast Gateway deepwater port 18 miles east of
Spectra Energy, formerly Duke Energy, will build a 16-mile subsea pipeline from its existing HubLine to the deepwater port site to transfer gas from the vessels into
Northeast Gateway will be the first new LNG importation facility to serve the east coast in more than 25 years. And it is the world"s second deepwater LNG importation facility.
The first, Gulf Gateway, 116 miles south of Cameron Parish,