Phase 14
-
SP Phase 14 refinery inauguration
SHANA (Tehran) – The South Pars (SP) Phase 14 refinery, the 13th and last onshore refinery of the giant gas field, southern Iran, has become operational.
-
Construction of South Pars refinery phase 14
TEHRAN (Shana) -- Phase 14 refinery is the last refinery of the twenty four phases of South Pars Gas Field, which is being constructed on a 170-hectare land in Kangan County, Bushehr province, southern Iran. Construction of the South Pars refinery phase 14 has reached 86% progress and it is expected that the first sweetening train of the refinery will be launched this winter.
-
South Pars Phase 14 Refinery Operational Next Year
TEHRAN (Shana) -- The operator of the South Pars Phase 14 development project said the project’s onshore refinery would come online in the first half of the next Iranian calendar year to March 21.
-
South Pars Phase 14 Refinery Online by June 2021
TEHRAN (Shana) – Operator of the South Pars Phase 14 development project said plans were devised to bring the project’s onshore refinery to full production tilt by June 2021.
-
Loading Phase 14 Platform
TEHRAN (Shana) -- The last offshore platform belonging to Phase 14 of the South Pars Gas Field has been loaded at the yard of Iran Marine Industrial Company (SADRA).
-
Last South Pars Phase 14 Platform Loaded
TEHRAN (Shana) – The last offshore platform belonging to Phase 14 of the South Pars Gas Field has been loaded at the yard of Iran Marine Industrial Company (SADRA).
-
Offshore Section of S.P Phase 14 Complete by December
TEHRAN (Shana) – The operator of phase 14 development project of the South Pars gas field said the offshore section of the project would be complete by December.
-
POMC Awarded Commissioning of SP 14
TEHRAN (Shana) -- Petropars Operation and Management Company (POMC) has been awarded a project to commission and operate Phase 14 of the supergiant South Pars gas field, Petropars CEO said.
-
SP14 Third Platform to Come On-stream in September
TEHRAN (Shana) -- The third production platform at Phase 14 of the giant South Pars gas field is set to become operational in September. The hookup operation for this platform that had been recently installed by HL-5000 vessel is now over. The platform is set to produce 14.1 mcm/d of gas.
-
3rd South Pars 14 Platform Installed
TEHRAN (Shana) -- The third offshore platform belonging to Phase 14 of the supergiant South Pars gas field has been successfully installed.
-
Loading Phase 14 Platform
BANDAR ABBAS (Shana) -- Loading of the third platform of Phase 14 project of the supergiant South Pars gas field.