According to MOGPC, while honoring the memory of the martyrs of the imposed war on the eve of the Holy Defense Week, said today's ability of the oil industry and reaching the goal of self-reliance is the result of the sacrifices of the martyrs and sacrificers.
He said: "Fortunately, despite economic constraints and special operational conditions, we managed to achieve our production goals and even beyond in the first half of the year.”
The official added: “In order to maintain the safety and environment around the company's facilities, we put the project of securing 16 kilometers of underground 6-inch pipelines of main liquids and 14-inch pipeline of main gas of the company's gas pressure boosting stations on agenda, which was completed on time.
The pipeline transmits 40 million cubic feet per day of Asmari Maroon gas from the Maroon 2 (Aghajari) and Maroon 5 complexes to NGL 700 and 800.