Peyman Imani made the remarks on Wednesday during a visit to inspect the 12-inch Dey field pipeline. He described progress on the project as satisfactory and said work is under way at a good pace on several fronts, including installing protective insulation coatings and laying and welding the pipes.
Referring to the funding secured for the project, he said the required pipes are being supplied quickly and delivered to the site in step with construction progress.
The ICOFC managing director said the 12-inch Dey pipeline will be 58 kilometers long. Despite the difficult terrain along its route, 25 kilometers have been completed so far, and construction is continuing toward the Dalan refinery.
Two New Wells Being Drilled in Dey Field
During the visit, Imani also went to the sites of the two wells currently being drilled in the Dey field and was briefed on the latest drilling operations. He said drilling on both wells is under way. Once they are completed and brought on stream, the field's gas output is expected to reach its maximum allowable rate for sustainable production, 5 million cubic meters per day.
He also announced the completion of the project to supply electricity to the field's wells and gathering center, saying several work fronts are running in parallel to develop the field.
Noting that infrastructure projects are being carried out in the field at the same time, he added that work to upgrade the field's main road is also in progress, including the construction of technical structures and several concrete bridge spans.
Sweet Gas: The Dey Field's Advantage
The Dey gas field is located in Farashband County, Fars Province, within ICOFC's operational area.
One of the field's advantages is that its gas is sweet. Unlike gas from many of the country's fields, it does not require extensive processing and sweetening.