According to NIDC, Kamil Babaei, head of the Fatah 52 drilling rig, said completion of the well which is located in the fields operated by Karoon Oil and Gas Production Company was planned for 45 days which was complete in only 34 days.
He noted: “During completion of the well, which was done by observing safety and specialized points, the wellhead equipment was replaced and while examining the well in terms of operation, lining and perforation, the surface was washed to the end.”