According to IOOC, oil production of these two wells is in stable conditions and has been stabilized with the help of artificial gas overflow.
After installation and commissioning of the S1 platform and the production of wells No. 61 and 64 in the Salman joint field, by carefully examining and conducting expert reports on drilling operations, completion and rehabilitation of two wells 62 and 63 and removing barriers and production problems were on the agenda of the exploitation engineering unit with the participation of Salman oil platform.
Despite the existing risks of non-production of these wells, increase of platform water production and the possibility of process problems, as well as the possibility of reducing oil production in Salman field due to allocating part of injected gas to other wells in this field to operate wells 62 and 63, the process of reviving the wells started with the best possible conditions.