According to the National Petrochemical Company (NPC), several key parts of the projects were installed during the current month including its primary reformer, ammonia production reactor as well as the CO2 separation tower all weighing over 1,500 tons together.
Only over the past 20 days, 11 percent of the items needed for completion of the ammonia unit of the project were installed in the facility.
The plant is being developed for 2,200 tons/day of ammonia production capacity in its first phase and 3,500 tons/day of urea and granule production capacity in its second phase development.
It is being built in Assaluyeh, southern Iran.