22 April 2019 - 16:23
  • News ID: 288559
NIDC Drills 7 Oil Wells in March/April

TEHRAN (Shana) -- The National Iranian Drilling Company (NIDC) has drilled 7 oil and gas wells over the course of the first month in the Iranian calendar from March 21 to April 20.

According to NIDC, Mohammad Ale-Khamis, deputy head of NIDC for drilling operations, said 4 of the wells were development and appraisal and the rest were workovers.

He said during the period, 14,466 meters of wells were spudded by NIDC rigs in the country.

The official further stated that drilling operations continued even on holidays, adding drilling of one of the wells came to an end 18 days prior to the planned deadline.

Ale-Khamis said 13 rigs were currently being transferred of which 7 were used for development drilling and 6 others for workover projects.

News ID 288559

Tags

Your Comment

You are replying to: .
0 + 0 =