6 October 2018 - 17:31
  • News ID: 284991
Forouzan 18F Platform Topside Loaded

TEHRAN (Shana) -- Load out operation of the topside of Platform 18F of Forouzan offshore oilfield is complete.

According to the Iranian Offshore Oil Company (IOOC), with continuous efforts, the 940-ton structure was loaded on Thursday at the yard of the Iran International General Contractor Company (IGC) in Qeshm Island, southern Iran.

The sea fastening operation of the topside for delivery to the oilfield would be carried out in two months.

After completing installation of the platform, it will be ready to dig 7 production wells as EPC/EPD projects.

The design, purchasing, construction, shipping and installation of a platform’s jacket, topside, pipelines and seabed cables were carried out by domestic experts and contractors.