The project is a year late because of delays in receiving the processing unit and site preparation delays at Melkøya, off the coast of
Snøhvit will send exports to the
Second train considered
Statoil is considering adding a second train to the 4.1 million tonne/year liquefaction plant but wants first to make its reserves "more robust" following other discoveries, said Rune Bjørnson, Statoil"s executive vice-president for natural gas.
He said the dispute between
The area in question, estimated to hold vast petroleum resources, has been unexplored over the past 30 years because of the dispute. However, both countries have signalled a willingness to start negotiations over the border, as their cooperation could enable them to tap into an estimated total of 40 billion boe of resources in the
"We are doing exploration in the Norwegian part of the Barents Sea," Bjørnson said, adding that the more attractive prospects appear to be in the eastern
Setting up a second train would be a matter of judgement, economics, and market expectations, Bjørnson said. One of the issues is the length of years a second train would be expected to produce LNG for exports. Although Statoil is "discussing the options" concerning the addition of a second train, Bjørnson emphasized that it was too early to be taking action and that the company"s focus "has been on train one."
Last week Statoil awarded the $36.6 million (220 million kroner) construction and technical on-site services contract to NCC Construction AS for the Hammerfest LNG plant that is being built on Melkøya island.
The 5-year contract, effective on May 1, includes maintenance of buildings and their technical systems, as well as some improvements and modifications. NCC Construction will have a permanent administrative staff of about five people at Melkøya.
Statoil said: "This is the last big contract relating to the operations phase of the Hammerfest LNG project."
PIN/OGJ.COM